PMI PMI-200 Braindumps PMI-200 dumps PMI-200 Exam PMI-200 Exam Dumps PMI-200 Practice Test PMI-200 Questions

Try These Latest and Valid PMI-Agile Certified Practitioner (PMI-ACP) PMI-200 Exam Questions

PMI Agile Certified Practitioner PMI-200 certification exam as a profession has an extraordinary evolution over the last few years. PMI-Agile Certified Practitioner (PMI-ACP) Software Development PMI-200 exam is the forerunner in validating credentials against PMI-200 exam. Here are updated PMI-200 exam questions, which will help you to test the quality features of DumpsSchool exam preparation material completely free. You can purchase the full product once you are satisfied with the product.

Vendor: PMI
Certifications: PMI Agile Certified Practitioner
Exam Name: PMI-Agile Certified Practitioner (PMI-ACP)
Exam Code: PMI-200
Total Questions: 145

♥ 2018 Valid PMI-200 Exam Questions ♥

PMI-200 exam questions, PMI-200 PDF dumps; PMI-200 exam dumps:: https://www.dumpsschool.com/PMI-200-exam-dumps.html (145 Q&A) (New Questions Are 100% Available! Also Free Practice Test Software!)

Latest and Most Accurate PMI-200 Dumps Exam Questions and Answers:

Question: 6

In reference to Scrum, each sprint should produce:

A. An increment of potentially shippable product functionality.
B. A set of documented product requirements and specifications.
C. A release with testable and measurable functionality.
D. An increment of potentially testable product functionality.

Answer: A
Get latest and Updated exam dumps [Latest 2018 dumps]
Question: 7

The primary purpose of a Sprint Review is for the team to:

A. Demonstrate what was accomplished during the sprint.
B. Discuss what went well, what didn’t, and ways to improve.
C. Prioritize and estimate stories planned for the next sprint.
D. Individually provide status updates on user stories in progress.

Answer: A

Question: 8

On what should Agile estimates be based?

A. A Work Breakdown Structure (WBS) from each iteration aligned with the project management plan
B. A disciplined iteration schedule, which improves predictability, combined with reaction to changes
C. Ball park figures collected from past Agile projects with scopes similar to the current project
D. Initial resource breakdown based on the available person days in the full project duration

Answer: B

Question: 9

A value stream map is a tool used to identify the:

A. Waste across the entire process.
B. Highest value product features.
C. Most valuable team interactions.
D. Most likely flow of project risks.

Answer: A

Question: 10

When estimating initial velocity, the team should most likely:

A. Discuss among the team their expectations of how many story points they can address.
B. Use a Kanban workflow to identify steps and calculate velocity.
C. Use velocity of past iterations or make a calculated guess.
D. Discuss with the customer their expectation for the velocity of producing the product.

Answer: C